Calculate the schedule variance schedule performance index


Your project to obtain charitable donations is divided into three activities.

The first activity is designed to solicit individual donations. It is scheduled to run the first 25 days of the project and to bring in $25,000. Even though we are 30 days into the project we still see that we have only 90% of this activity complete.

The second activity relates to company donations and is scheduled to run for 30 days starting on day 5 and extending through day 35.We estimate that even though we should have (25/30) 83% of this activity complete, it is actually only 50% complete. This part of the project was scheduled to bring in $150,000 in donations.

The final activity is for matching funds. This activity is scheduled to run the last 10 days of the project and has not started. It is scheduled to bring in an additional $50,000. So far $175,000 has actually been brought in on the project.

Calculate the schedule variance, schedule performance index, and cost (actually value in this case) performance index. How is the project going?

Hint: Note that this problem is different since revenue rather than cost is the relevant measure. Use care in how the measures are interpreted. Operations Management

Solution Preview :

Prepared by a verified Expert
Project Management: Calculate the schedule variance schedule performance index
Reference No:- TGS01130295

Now Priced at $60 (50% Discount)

Recommended (93%)

Rated (4.5/5)