Problem
The demand for an item is normally distributed with an average annual demand of 8000 units and with a standard deviation of demand during the lead time of 6 units. The lead time for this item is a constant 3 days. Calculate the reorder point using a 95 percent in-stock probability (Z = 1.65) and assuming 365 days per year.