Question: Given the following information, calculate the purchasing department's efficiency variance. Standard number of transaction per day 20 Standard labor cost per day $200 Actual number of days for processing transactions 120 Actual number of transactions processed 1,960 Actual labor cost per day $180 Multiple choice question. $2,400 unfavorable $4,400 favorable $2,400 favorable $4,400 unfavorable