Calculate the projects expected npv


Question:

Company A is considering a proposed project whose estimated NPV is 12 million. The estimate assumes that economic conditions will be "average". However the CFO realizes that conditions could be better or worse, so a scenario analysis was performed and the following results were obtained;

Economic Scenario Prob. of Outcome NPV

Recession .05 (70 million)

Below Average .20 (25 million)

Average .50 12 million

Above average .20 20 million

Boom .05 30 million

Calculate the projects expected NPV, standard deviation, and coefficient of variation. Please show calculations.

Solution Preview :

Prepared by a verified Expert
Finance Basics: Calculate the projects expected npv
Reference No:- TGS02044744

Now Priced at $20 (50% Discount)

Recommended (92%)

Rated (4.4/5)