Calculate the project's coefficient of variation. (Hint: Use the expected NPV.) Squared dev. Prob. NPV NPVi - E(NPV) Squared deviation times probability 0.24 $6,289.81 $5,829 $ $ 0.24 -$2,390.74 -$2,852 $ $ 0.32 -$1,233.33 -$1,694 $ $ 0.20 -$ 400.00 -$861 $ $ ____________ 1.00 $ 461.11 Variance $_____________ Standard deviation $