You manage a casting company that produces bronze valves on a 10 person assembly line. You produce 160 valves on an 8 hour shift.
a. Calculate the productivity of the line
b. You change the layout to increase production to 180 valves on an 8 hour shift. What is the new labor productivity per hour
c. What is the percentage of productivity increase?