Calculate the processing load, available capacity, and develop the load profile for the stero speaker subassembly. Two employees work the assembly process for 40 hours each.
a. complete the load chart
b. prepare a load profile chart from this data
c. as the planner, what concerns do you have and what changes would you make if any?
Processing Time=20 mins week 1 2 3 4 5 6 7 8
Planned Order Releases 220 190 210 270 210 190 240 200
Processing Load (hrs)
Available Capacity (hrs)