Calculate the processing load and develop the load profile for the computer assembly process. As the planner, what concerns do you have (if any)? What changes might you consider?
Part Name: Computer
|
Processing time 5
|
Week
|
Week
|
Week
|
Week
|
Week
|
Week
|
Week
|
Week
|
2 hours
|
1
|
2
|
3
|
4
|
5
|
6
|
7
|
8
|
Planned order releases
|
60
|
50
|
40
|
35
|
70
|
55
|
45
|
60
|
Processing load (hours)
|
|
|
|
|
|
|
|
|
Available capacity (hours)
|
120
|
120
|
120
|
120
|
120
|
120
|
120
|
120
|