Calculate the processing load and available capacity, and develop the load profile for the stereo speaker subassembly. Two employees work the assembly process for 40 hours each. As the planner, what concerns do you have and what changes would you make (if any)?
Part Name: Stereo speaker
|
Processing time 5
|
Week
|
Week
|
Week
|
Week
|
Week
|
Week
|
Week
|
Week
|
20 minutes
|
1
|
2
|
3
|
4
|
5
|
6
|
7
|
8
|
Planned order releases
|
210
|
180
|
220
|
260
|
200
|
180
|
230
|
190
|
Processing load (hours)
|
|
|
|
|
|
|
|
|
Available capacity (hours)
|
|
|
|
|
|
|
|
|