Bibing Kah Ltd has estimated that they will incur $285,050 overhead cost next year. The company uses activity based costing to allocate OVH to each job. Here is the breakdown per activity:

Activities

Estimated MOH

Estimated Bases

Allocation Base

Procurement

$ 300.00

10 PO

# of purchase orders

Machine setup

$ 7,000.00

35 Setups

# of setups

Insertion of parts

$ 112,000.00

4,000 parts

# of parts

Finishing

$ 150,000.00

2,500 DL hours

# of finished DL hours

Shipments

$ 15,000.00

10 shipments

# of shipments

Invoicing

$ 750.00

10 Invoices

# of completed invoices

Total

$ 285,050.00



Calculate the pre determined rate for each activity.