Problem
You are the project coordinator for Capitol Records, an American major record label located in Los Angeles, California. The roof of the main office building was severely damaged by a hailstorm several days ago and a project was quickly launched to replace it with a more modern hail-resistant roof. The timeline for this project is extremely tight. As the project coordinator, you are responsible for ensuring effective communication across the entire project team.
• The stakeholders are:
• Facilities Manager
• Plant Manager
• Human Resources
• Security
• Roofing Contractor
Communication between any of the stakeholders is likely during the project. Calculate the number of lines of communication between them. Show any calculations needed to get the answer.