You are working on a 20 months project. There are 35 stakeholders in total, excluding yourself. Six months into the project, you are given the following information: PV = $60,000, EV = $43,000, AC = $46,000, BAC = $500,000 a) Calculate the number of channels of communications for this project. Discuss why it is important to have good communications in the project.