Calculate the NPV value for Project A and B as shown in the following table using each of the discount rates 8% and 12%. For each discount rates, decide which one is best project. What can you conclude from the result? Check if the projects are worth taking up when the rate of interest on borrowed capital is 15%.
Year Project A Project B
0 -8000 -10000
1 1000 2000
2 2000 2000
3 4000 6000
4 3000 2000
5 9000 2000
6 -6000 2000