Q: The MPS calls for 120 units of Product M. There are currently 30 of Product M on hand. Each M requires four of Component N. There are 20 units of N on hand.

(a) Calculate the net requirements for M.

(b) Calculate the gross requirements for N.

(c) Calculate the net requirements for N.