Calculate the net present values for project a and project


A company is considering two equally risky mutually exclusive projects. The relevant cash flows

are as follows:

Period Project A Project B

0 -$285,000 -$270,000

1 100,000 110,000

2 100,000 100,000

3 100,000 90,000

4 100,000 80,000

i. Calculate the Net Present Values for project A and project B assuming the company’s required rate of return is 14%. Which project should the company choose?

ii. Calculate the profitability index for project A and project B.