A part is made in batch sizes of 900 units which require 7 operations. Each operation has an average setup time of 83 minutes and 4.5 hrs of nonoperation time. The average operation time is only 2.2 sec/pc.
A) Calculate the Manufacturing Lead Time for this part.
B) Calculate the Work In Progress if the plant runs three 8 hour shifts a day.