Problem: Aco manufactures blankets. Manufacturing standards per blanket, based on 5,000 blankets per month as follows:
Direct material of 3 yards at $5,00 per yard
Direct labor of 2,50 hours at $17,00 per hour
Overhead applied per blanket at $17,00
In the month of April, the company actually produced 5,100 sleeping bags using 27,000 yards of material at a cost of $5.50 per yard. The labor used was 11,500 hours at an average rate of $17.25 per hour. The actual overhead spending was $96,000.
Required: Calculate the Labor rate variance.