Calculate the following cost variance schedule variance


You are given the following information for a 12 month project:

BCWS (PV) = $20,000, BCWP (EV) = $15,000, ACWP (AC) = $23,000,    Budget at Completion (BAC) = $120,000.

Calculate the following:

a. Cost Variance

b. Schedule Variance

c. Cost Performance Index (CPI)

d. Schedule Performance Index (SPI)

e. Estimate at completion costs (EAC)