You are given the following information for a 12 month project:
BCWS (PV) = $20,000, BCWP (EV) = $15,000, ACWP (AC) = $23,000, Budget at Completion (BAC) = $120,000.
Calculate the following:
a. Cost Variance
b. Schedule Variance
c. Cost Performance Index (CPI)
d. Schedule Performance Index (SPI)
e. Estimate at completion costs (EAC)