Calculate the expected project completion time


Assignment:

Calculate the ES, EF, LS, and LF times and the slack for each activity inthe figure below, and identify the critical path for the project. Can the project be completed in 30 weeks? Assume that "Systems Analysis" actually finished at 8 weeks, "Design Input & Output" actually finished at 15 weeks, and "Design Database" actually finished at 19 weeks. Recalculate the expected project completion time. Which activities would you focus on in order to get the project back on schedule?

Request for Solution File

Ask an Expert for Answer!!
Project Management: Calculate the expected project completion time
Reference No:- TGS03030090

Expected delivery within 24 Hours