Discuss the below:
Q: The following represents a project that should be scheduled using CPM:
|
IMMEDIATE PREDECESSORS |
TIMES (DAYS) |
ACTIVITY |
a |
m |
b |
A |
- |
1 |
4 |
7 |
B |
- |
1 |
3 |
5 |
C |
A |
2 |
5 |
11 |
D |
A |
1 |
8 |
9 |
E |
B |
1 |
2 |
3 |
F |
C,D |
1 |
6 |
11 |
G |
D,E |
1 |
2 |
3 |
H |
F,G |
2 |
3 |
3 |
|
a. What is the critical path?
b. What is the expected project completion time?
c. What is the probability of completing this project within 22 days?