Calculate the expected npv for both projects


Task: Trail Guides, Inc., is currently evaluating two mutually exclusive investment. After doing a scenario analysis and applying probabilities to each scenario, they have determine that the investments have the following distributions around the expected NPVs.

Profitability NPV A NPV B
15% -$40,000 -$15,000
20% -10,000 2,500
30% 20,000 20,000
20% 50,000 37,500
15% 80,000 55,000

Several members of the management team have suggested that Project A should be selected because it has a higher potential NPV. Other members have suggested that Project B appears to be more conservative and should be selected. They have asked you to resolve this question.

a. Calculate the expected NPV for both projects. Can the question be resolved with this information alone?

b. Calculate the variance and standard deviation of the NPVs for both projects. Which project appears to be riskier?

c. Calculate the coefficient of variation for both projects. Does this change your opinion from part b?

d. Calculate the probability of a negative NPV for both projects.

e. Which project should be accepted?

Solution Preview :

Prepared by a verified Expert
Finance Basics: Calculate the expected npv for both projects
Reference No:- TGS01833619

Now Priced at $25 (50% Discount)

Recommended (97%)

Rated (4.9/5)