Given an activity in a mobile app design project whose planned cost was $25,000 but actual cost to date is $22,000 so far, and whose estimated progress is 80%, calculate the cost and schedule variances. Also find the CPI and SPI. Then find the critical ratio of the project. Finally, calculate the ETC and EAC for the project. Will the client be pleased or angry?