Calculate the earned value of a work item


Question: Calculate the earned value of a work item based on the following criteria: Actual labor dollars (expended) = $2000.00, estimated labor dollars = $1000.oo, Percent Complete= 10%, Schedule of work item = During 4th week of the schedule. Note: some info above is not needed for calculation