Calculate the earliest start es latest start ls earliest


Management in the R&D department is planning to bid on a large project for the development of a new communication system for commercial planes. They plan to use CPM to develop the project which has the following activities, durations (in weeks), and precedence relationships:

Activity Predecessors Duration

A

- 3
B

a

2
C a 4
D a 4
E b 6
F c,d 6
G f 2
H d 3
I e,g,h 3

Calculate the earliest start (ES), latest start (LS), earliest finish (EF), latest finish (LF), and slack for each activity.