Exercise 1: A project has been defined to contain the following list of activities along with their required times for completion.
Activity No.
|
Activity
|
Time (weeks)
|
Immediate Predecessors
|
1
|
Collect requirements
|
3
|
|
2
|
Analyze processes
|
2
|
1
|
3
|
Analyze data
|
2
|
2
|
4
|
Design processes
|
6
|
2
|
5
|
Design data
|
3
|
3
|
6
|
Design screens
|
2
|
3,4
|
7
|
Design reports
|
4
|
4,5
|
8
|
Program
|
5
|
6,7
|
9
|
Test and Document
|
7
|
7
|
10
|
Install
|
2
|
8,9
|
a. Draw a Network diagram for the activities.
b. Calculate the earliest expected completion time.
c. Show the critical path
d. What would happen if activity 6 were revised to take 6 weeks instead of 2 weeks?
Exercise 2: Construct a Gantt chart for the project defined in Problem and Exercise 1.
Attachment:- Gantt-Chart-Template.rar