Jaster Corporation's management keeps track of the time it takes to process orders. During the most recent month, the following average times were recorded per order:
|
Days |
Wait time |
13.9 |
Inspection time |
0.3 |
Process time |
2.65 |
Move time |
1.3 |
Queue time |
3.7 |
|
Required: |
a. |
Compute the throughput time. (Round your answer to 2 decimal places.)
|
b. |
Compute the manufacturing cycle efficiency (MCE). (Do not round intermediate calculations. Round your answer to 2 decimal places.)
|
c. |
What percentage of the production time is spent in non-value-added activities? (Do not round intermediate calculations. Round your answer to nearest whole percentage. Omit the "%" sign in your response.)
|
Percentage of the production time |
% |
d. |
Compute the delivery cycle time. (Round your answer to 1 decimal place.)
|