Calculate the Daily Standard Production Rate of Equipment
An excavator with a bucket capacity of 3-yd3 has a standard operating cycle time of 40 seconds. The daily standard production rate of the excavator is most nearly:
Solution: The daily standard production rate is as follows:
Pday = (3yd3)(8hr)(3,600sec/hr)/(40sec)= 2,160 - yd3