calculate the daily standard production rate of


Calculate the Daily Standard Production Rate of Equipment

An excavator with a bucket capacity of 3-yd3 has a standard operating cycle time of 40 seconds. The daily standard production rate of the excavator is most nearly:

 Solution: The daily standard production rate is as follows:   

Pday = (3yd3)(8hr)(3,600sec/hr)/(40sec)= 2,160 - yd3