Calculate the critical volume then estimate the green time


Calculate the critical volume then estimate the green time interval for each phase of the intersection using the data provided below. Assume that the intersection will operate as a simple two phase cycle with a 90 second cycle length. Please also assume 2 lanes per intersection approach.

 

Yellow + all-red is 4.5 seconds / phase

Northbound peak hour volume is 460 vph

Southbound peak hour volume is 700 vph

Westbound peak hour volume is 760 vph

Eastbound peak hour volume is 860 vph

Request for Solution File

Ask an Expert for Answer!!
Civil Engineering: Calculate the critical volume then estimate the green time
Reference No:- TGS0649459

Expected delivery within 24 Hours