Use the given project information.
Activity Activity Time(weeks) Immediate Predecessor(s)
A 3 none
B 4 A
C 2 B
D 5 B
E 4 C
F 3 D
G 2 E,F
Calculate the completion time for the project. (Completion time = weeks)
Determine which activities are included on the critical path.
A, B, D, F, G
A, B, C, E, G