Problem:
A project has an expected risky cash flow of $500, in year 4. The risk-free rate is 4%, the market rate of return is 13%, and the project's beta is 1.2.
Required:
Question: Calculate the certainty equivalent cash flow for year 4.
Note: Provide support for rationale.