Clap Off Manufacturing uses 1,300 switch assemblies per week and then reorders another 1,300. Assume the relevant carrying cost per switch assembly is $5 and the fixed order cost is $575.
Calculate the carrying costs.
Calculate the restocking costs.
Calculate the EOQ number of orders per year.