Suppose that the overhead costs are divided between two activities as follows:
Machining $632,000
Inspection 360,000
Required:
1. Calculate predetermined overhead rates for the two activities, machining and inspection.
2. Suppose a job used 4,000 machine hours and 800 inspection hours. If the job size is 8,000 units, what is the overhead cost per unit?