Problem:
Price variance 12,000 U
Usage variance 9,000 F
The standard cost for material is $2 per pound and three pounds per unit. 20,000 units were produced. The purchase price variance was .30 per pound.
Calculate:
a. Pounds purchased
b. Pounds used