Calculate optimum production batch size, production run, annual production rate, lead time, safety stock, and total annual cost, length of a production run, and cycle time with help of following information:
Annual demand: 21,000,000
Annual holding cost per unit: $1
Production rate: 3 bars per second
Set up cost: 450