Calculate multifactor productivity


Assignment:

I. Productivity. The manager of a crew that installs wood floors has tracked the crew's output over the past several weeks. Each worker works hours per week, and earns $19 per hour. The wholesale cost of lumber to the company is $6 per square foot, and the company charges its customers $21 per square foot of flooring installed.

Week   Crew Size   Lumber Used (sq. ft)  Flooring Installed (sq.ft)
 1         6                480                          430
 2         4                381                          335
 3         2                260                          228
 4         5                525                          487

a. Calculate labor productivity for each of the weeks shown.

b. Suppose that in addition to cost and wholesale lumber cost the firm's overhead is 140% of its labor cost. Calculate multifactor productivity for each week shown

II. In a few paragraphs, explain why

a. Productivity is important concept to a business or government entity

b. Measuring productivity is also very important to an entity.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Calculate multifactor productivity
Reference No:- TGS02945403