Problem
At Marx, the standard quantity of labor is 23 hours per refrigeration unit. The standard wage rate is $35. In July, the company produced 80 refrigeration units and incurred 2,000 labor hours at a cost of $68,000.
Calculate the labor rate variance and the labor efficiency variance. Indicate whether the variances are favorable or unfavorable.