Planned Value = $41,000
Earned Value = $38,000
Actual Cost = $42,000
Budget At Completion = $252,000
A. Calculate how long it will take to finish project
B. Create the earned value chart of this project. Assume the data for month 1 is half the values given.
Original time estimate is one year