Calculate expected time or duration for each activity


Project path A-C-E-J has these activity time estimates in days:

Activity                 Optimistic                   Most Likely                Pessimistic

     A                             3                                  4                                   5

     C                             9                                12                                 14

     E                           12                                15                                 20

     J                              7                                  9                                   9

Compute the expected time or duration for each activity, the variance for each activity, and the expected duration and variance for the path.

Request for Solution File

Ask an Expert for Answer!!
Mathematics: Calculate expected time or duration for each activity
Reference No:- TGS0546221

Expected delivery within 24 Hours