Project path A-C-E-J has these activity time estimates in days:
Activity Optimistic Most Likely Pessimistic
A 3 4 5
C 9 12 14
E 12 15 20
J 7 9 9
Compute the expected time or duration for each activity, the variance for each activity, and the expected duration and variance for the path.