You are the project manager on a project that has $800,000 budget. There are two teams that will work for six month for a total of 10,000 hours. According to the project schedule your team should be done with 38% of the work. As of today, the project is 40% complete while 50% budget has been used. Calculate CV, PV, CPI, SPI, and share your conclusion.