Problem: The progress report of a project contains the following data about the project costs:
BCWS = $ 46,500
BCWP = $ 49,200
ACWP = $ 54,250
BAC = $ 183,600
a.) Calculate CV
b.) Calculate CVP
c.) Calculate CPI
d.) Calculate SV
e.) Calculate SVP
f.) Calculate SPI
g.) Calculate EAC
h.) Calculate VAC
i.) Comment on the way the project is progressing.