Assignment:
Six Sigma:
Consider two processes A and B each with sample size of n = 5
Process A: Mean = 100 Sample Standard deviation = 3
Process B: Mean = 105 Sample Standard deviation =1
Specifications are 100 ± 10,
a. Calculate Cp and Cpk for each process and interpret these ratios
b. Which process should be preferred and why?