Assignment: PMO Meeting- MobileGo Project Recovery
The project management office or project office (PMO) is concerned that the MobileGo project is behind schedule and in danger of being late. Assume that a project meeting has been scheduled so that you and your project team can propose a course of action to reduce the project schedule. The PMO has provided your team with project simulation data spreadsheet .To prepare for this PMO meeting, carry out the following:
a. Analyze the data provided in the spreadsheet, and calculate at least two options for crashing the schedule.
b. Identify likely risks associated with your revised schedule as well as your strategy for their mitigation.
c. Evaluate concerns associated with the motivation of the team given the increase in project complexity, the additional overtime, and the high-pressure environment that the team is likely to face.
d. Explain the steps you will take as project manager to hold the team together and keep it functioning despite the difficulty.
Complete the crash calculations and options in a Word or Excel document, and submit it for grading. Additionally, you will create a PowerPoint presentation of at least 10 slides that explains your crash plan as well as your overall plan to successfully lead the team to the finish line.
Format your assignment according to the give formatting requirements:
a. The answer must be double spaced, typed, using Times New Roman font (size 12), with one-inch margins on all sides.
b. The response also includes a cover page containing the title of the assignment, the course title, the student's name, and the date. The cover page is not included in the required page length.
c. Also include a reference page. The references and Citations should follow APA format. The reference page is not included in the required page length.