Suppose you calculate a project's net present value to be $10 million. What does this mean? Suppose you calculate a project's profitability index to be 1.3. What does this mean? uppose you calculate a project's net present value to be $30 million. If the required outlay for this project is $100 million, what is the project's profitability index?