Calculate a fixed period system with a 90% service cycle level
Demand for widgets is 52,000 widgets/year
Ordering Cost is $60 per order. Unit Cost is $5.00
The Carrying Charge is 20%
Demand is 1000 per week
Lead Time is 2 weeks
Standard deviation of demand is 300/week
Calculate a fixed quantity system with 90% service cycle level.