Demand for widgets is 52,000 widgets/year.
Ordering Cost is $60 per order.
Unit Cost is $5.00
The Carrying Charge is 20%
Demand is 1000 per week
Lead Time is 2 weeks
Standard deviation of demand is 300/week
Calculate a fixed period system with a 90% service cycle level