Building a swimming pool
Create a Gantt chart from the work breakdown structure.
Create a PERT/CPM network showing the interdependencies of the different activities.How long will the project take? (Note:Don’t forget to take “elapsed time” into account.)
Using the information in your Gantt chart, as well as the information on wage rates and cost of materials, put together a budget showing planned total expenditures for the project.