Question - Buerhle Company purchased (at a cost of $11,650) and used 2,380 pounds of materials during May. Buerhle's standard cost of materials per unit produced is based on 2 pounds per unit at a cost $5 per pound. Production in May was 1,090 units.
Compute the total, price, and quantity variances for materials.