Please help me on this problem I am stuck! I got situation 1 and 2 but after that the answers are wrong even though I am doing everything exactly how I got the answer of situatio 1 and 2. Please help me
Brady Construction Company contracted to build an apartment complex for a price of $6,000,000. Construction began in 2016 and was completed in 2018. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars.
|
|
|
|
|
|
|
Estimated Costs to Complete
|
|
Costs Incurred During Year
|
(As of the End of the Year)
|
Situation
|
2016
|
2017
|
2018
|
2016
|
2017
|
2018
|
1
|
1,600
|
|
2,430
|
|
1,200
|
|
3,630
|
|
1,200
|
|
-
|
|
2
|
1,600
|
|
1,200
|
|
2,800
|
|
3,630
|
|
2,800
|
|
-
|
|
3
|
1,600
|
|
2,430
|
|
2,400
|
|
3,630
|
|
2,300
|
|
-
|
|
4
|
600
|
|
3,100
|
|
1,200
|
|
4,200
|
|
925
|
|
-
|
|
5
|
600
|
|
3,100
|
|
2,000
|
|
4,200
|
|
2,300
|
|
-
|
|
6
|
600
|
|
3,100
|
|
2,800
|
|
5,600
|
|
2,600
|
|
-
|
|
|
|
Gross Profit (Loss) Recognized
|
|
Percentage of Completion
|
Completed Contract
|
Situation
|
2016
|
2017
|
2018
|
2016
|
2017
|
2018
|
1
|
|
|
|
|
|
|
2
|
|
|
|
|
|
|
3
|
|
|
|
|
|
|
4
|
|
|
|
|
|
|
5
|
|
|
|
|
|
|
6
|
|
|
|
|
|
|