Problem: The attachment has a network, with all times indicating weeks, answer the following questions:
1) What is the impact on the end date of the project if activity B slips by two weeks?
2) What is the impact on the end date of the project if activity E slips by one week?
3) What is the impact on the end date of the project if activity D slips by two weeks?
4) If the customer offered you a bonus for completing the project in sixteen weeks or less, which activities would you focus on first as part of compression ("crashing") analyses?