Bonus for completing the project


Problem: The attachment has a network, with all times indicating weeks, answer the following questions:

995_Business management.jpg

1) What is the impact on the end date of the project if activity B slips by two weeks?

2) What is the impact on the end date of the project if activity E slips by one week?

3) What is the impact on the end date of the project if activity D slips by two weeks?

4) If the customer offered you a bonus for completing the project in sixteen weeks or less, which activities would you focus on first as part of compression ("crashing") analyses?

Solution Preview :

Prepared by a verified Expert
Project Management: Bonus for completing the project
Reference No:- TGS01444133

Now Priced at $20 (50% Discount)

Recommended (91%)

Rated (4.3/5)