bloomsday outfitters produces t-shirts for road


Bloomsday Outfitters produces T-shirts for road races. They need to acquire some new stamping
machines to produce 30,000 good T-shirts per month. Their plant operates 200 hours per month, but
the new machines will be used for T-shirts only 60 percent of the time and the output usually includes
5 percent that are "seconds" and unusable. The stamping operation takes 1 minute per T-shirt, and the
stamping machines are expected to have 90 percent efficiency considering adjustments, changeover of
patterns, and unavoidable downtime. How many stamping machines are required?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: bloomsday outfitters produces t-shirts for road
Reference No:- TGS0202578

Expected delivery within 24 Hours